Completed March 2026
Kettering, Northamptonshire
Get to know our client
Alpro is a pioneering European plant-based food and drink company founded in 1980. As of 2021, it is now one of the highest certified food and drink organisations in the UK, as its B Corp accreditation has improved.
The company is committed to helping people make positive food choices by producing nutritious, sustainable plant-based alternatives, including oat, soya, almond and coconut products. With a strong focus on health, innovation and environmental responsibility, Alpro sources quality ingredients, works closely with its farming partners and continually invests in manufacturing and product development to reduce its environmental impact.
Main Scope of Works
A full Strip out of existing canteen and old laboratories
Specialist removal of Fume Cupboards and contaminated ductwork and extraction
Installation of new ceilings with new lighting
Formation of new corridor using plasterboard partitions and glass viewing windows
New vinyl flooring
Supply and installation of new fully equipped kitchenette and bar seating areas
Creation of break out areas with TV accessibility creating a relaxed environment for staff
Validation and modifications to the existing HVAC system
Fire alarm modifications
Decorations to all walls & doors
Installation of new electrical supplies
The project involved the strip out of the old canteen and laboratories that were left redundant following our creation of the new facility for the site in 2025. The new canteen was created combining the two areas to produce a ‘double in’ sized, modern facility, delivering traditional eating areas, breakfast bar step-up eating spaces, as well as sofa break out areas with tv’s, fridges and charging points. The new space was designed to enhance staff wellbeing, improving day to day working, allowing staff to remove themselves and relax fully during their breaks. Whilst we were creating this area, we ensured all relevant technical requirements were met.
As part of the project, a new corridor was formed separating Alpro’s entrance and admin facilities from the newly formed canteen and breakout areas. We created and altered partition walls and on the canteen side, we installed half partition wall and half glass, which we had muralled to allow lots of natural light to flood into the canteen areas from the entrance. This was completed with the aim of keeping staff and their wellbeing at the heart of this project.
Working to a 12-week programme, the project was carefully planned and coordinated to ensure a smooth delivery within a live working environment. A comfortable temporary canteen was set up at the start of the project to allow staff to facilitate all breaks, which remained in place until the opening of the new facility. Attention was given to layout, services coordination, and finishes to provide a fit for future staff canteen and providing additional space to accommodate Alpro’s growing operational needs.