Completed November 2025
Kettering, Northamptonshire
Get to know our client
Alpro is a pioneering European plant-based food and drink company founded in 1980. As of 2021, it is now one of the highest certified food and drink organisations in the UK, as its B Corp accreditation has improved.
The company is committed to helping people make positive food choices by producing nutritious, sustainable plant-based alternatives, including oat, soya, almond and coconut products. With a strong focus on health, innovation and environmental responsibility, Alpro sources quality ingredients, works closely with its farming partners and continually invests in manufacturing and product development to reduce its environmental impact.
Main Scope of Works
Refurbishment and fit-out of an existing unoccupied space to create 4 laboratories, 1 store and 2 offices
Construction of new partition walls, including hygienic wall cladding to laboratories and decorated office, store and corridor partitions
Installation of glazed partitions, internal and external doors, a fast-action roller door, and new windows, pass-through hatches and fire exits
Application of new epoxy resin flooring, suspended ceilings and thermal insulation throughout
Supply and installation of laboratory furniture, specialist equipment, wash stations and sinks
Installation of new HVAC systems, specialist ventilation and three fume cupboards
Delivery of new mechanical and plumbing services, including below-ground drainage, water services and compressed air to the PH Lab
Complete electrical installation, including lighting, fire-rated enclosure, fire alarm modifications, access control and CCTV upgrades
Fire stopping to all new and existing service penetrations
Supply and installation of a new ProfilGate contamination control system
iab-Lab delivered a full refurbishment and fit-out for Alpro, creating modern, purpose-built laboratory and workplace environments to support their growing operational needs.
The project involved the fit-out of four new laboratories, a central store, a new entrance corridor, and two offices, replacing facilities that were previously outdated, undersized, and no longer fit for purpose. The new spaces were designed to improve functionality, efficiency, and day-to-day working conditions, while meeting the technical requirements of a contemporary laboratory environment.
The installation of the new ProfilGate proved a first for iab-Lab, a system predominantly used in food manufacturing settings to prevent contaminants from entering sensitive production and logistics areas. With only one specialist in the UK able to deliver this type of equipment, we worked closely to ensure a successful installation despite its technicalities.
Working to a 16-week programme, the project was carefully planned and coordinated to ensure a smooth delivery within a live working environment. Attention was given to layout, services coordination, and finishes to provide clean, modern spaces that support both laboratory processes and office use.
The completed fit-out provides Alpro with a significantly enhanced working environment, future-proofed to accommodate their ongoing development and operational demands.