Completed July 2017
Contract Value £215,000
Wellingborough, Northamptonshire
Get to know our client
Scott Bader is a global manufacturer of advanced composite materials, adhesives and functional polymers, supplying innovative material solutions to industries including marine, construction, transportation, renewable energy and manufacturing. Headquartered in Northamptonshire, serving 90+ countries with 18 locations worldwide, the company is recognised for its commitment to innovation and sustainability.
Main Scope of Works
Complete turnkey refurbishment of an existing polymer development laboratory
Full laboratory design, fit-out and installation
Mechanical and electrical (M&E) services installation
Bespoke ventilation and air handling system
Installation of standard and walk-in fume cupboards
Laboratory furniture and associated fixtures and fittings
CAT 5 break tank installation to serve the new and existing laboratory facilities
We were approached by Scott Bader to discuss the refurbishment of an existing Polymer Development Laboratory. From the initial client meeting, iab-Lab delivered a complete turnkey laboratory solution, managing the project from concept design through to installation. With no existing building drawings available, our team carried out a full site survey to establish the building layout and develop a detailed design tailored to the client’s operational requirements.
The primary challenge surrounded the air volume extracted from a total of seven fume cupboards. To achieve this, the laboratory was divided into two separate rooms, one housing five standard fume cupboards and the other having one standard and one walk-in fume cupboard, with dedicated air handling units (AHUs) serving each area. The larger AHU was designed with a two-stage fan, allowing the client to operate different banks of fume cupboards independently while automatically balancing the supply air to suit demand, improving both efficiency and safety.
Air conditioning was installed in both laboratories to manage the additional heat generated by specialist equipment. As the building had recently received a new roof lining, the extract system was designed to utilise an existing external opening, avoiding any roof penetrations. Fresh air was introduced through a modified window opening, providing a practical solution while preserving the building fabric.
To complete the fit-out, iab-Lab supplied laboratory furniture designed to match the client’s existing facilities and installed a CAT 5 break tank to provide a reliable water supply for both the new laboratory and the wider laboratory areas within the building.
The completed project delivered a modern, fully integrated laboratory environment with intelligent ventilation control, high-quality laboratory furnishings, and mechanical services designed to support safe, efficient, and future-proof laboratory operations.