Vaccitech, now known as Barinthus Bio, is a clinical-stage biopharmaceutical company focused on developing next-generation immunotherapies to treat autoimmune and inflammatory diseases. An emerging leader in the field of antigen-specific immunotherapy, the company is advancing innovative treatments designed to harness the body’s immune system and guide T-cell responses to address complex medical conditions.
iab-Lab successfully delivered the transformation of five individual industrial units into a single, integrated three-storey laboratory and office facility. This extensive conversion project required complex structural alterations, technical installations, and a coordinated approach to specialist compliance requirements.
A major feature of the works was the installation of two new mezzanine levels, one spanning all five units to form a new first floor, and an additional mezzanine within units 9 and 10 to create a second floor. The ground floor consisted of brand new laboratories throughout. A mixture of open plan and private management offices, with a canteen and separate break out area were constructed on the first floor. The second floor included another open plan break out/training space, as well as three brand new glazed meeting rooms with a tea point. To suit the new layout, a fully DDA-compliant three-storey lift was installed.
The facility now benefits from a range of advanced systems including a fully integrated BMS, new fume cupboards with extraction systems, and a Cryo Lab emergency extraction system. We also installed specialist gas generation and detection equipment, including liquid nitrogen (N2) and compressed air (CA) systems. To meet stringent standards of their CL2 laboratories, this area was designed and constructed to comply with ISO201501-4. Rockfon Medicare Air ceiling tiles were installed to a number of the labs to satisfy HTM60 healthcare requirements.
Further works included a full upgrade of incoming mains power by SSE, including groundworks, the installation of an external generator, and the formation of new below-ground drainage channels. Throughout the project, iab-Lab managed all landlord licence to alter documentation, ensuring full regulatory compliance and a smooth delivery process from start to finish.